[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931101":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931101,603,1,"单选题","关于关键线路和关键工作叙述不正确的有( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在网络计划中，总时差最小的作为关键工作",false,{"key":16,"text":17,"correct":14},"B","从起点节点到终点节点的通路中，各项工作持续时间总和最大的是关键线路",{"key":19,"text":20,"correct":14},"C","关键线路上可能有虚工作存在",{"key":22,"text":23,"correct":24},"D","开始节点和完成节点均是关键节点的工作一定是关键工作",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]