[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931100":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931100,603,2,"多选题","在采用强制确定法选择价值工程分析对象时，下列说法正确的是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","若价值系数远远小于1，则应对评价对象进行价值工程分析",true,{"key":16,"text":17,"correct":14},"B","若价值系数远远小于1，说明评价对象所耗成本较高，存在降低成本的潜力",{"key":19,"text":20,"correct":21},"C","若价值系数远远大于1，说明评价对象所耗成本较高，存在降低成本的潜力",false,{"key":23,"text":24,"correct":21},"D","若价值系数等于1，说明评价对象成本过高",{"key":26,"text":27,"correct":14},"E","若价值系数等于1，说明评价对象的功能重要程度与成本的比重属合理匹配","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]