[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931096":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931096,603,1,"单选题","在某工程网络计划中，已知工作M的总时差和自由时差分别为4天和2天，监理工程师检查实际进度时发现该工作的持续时间延长了5天，说明此时工作M的实际进度( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","既不影响总工期，也不影响其后续工作的正常进行",false,{"key":16,"text":17,"correct":14},"B","不影响总工期，但将其紧后工作的开始时间推迟5天",{"key":19,"text":20,"correct":14},"C","将其后续工作的开始时间推迟5天，并使总工期延长3天",{"key":22,"text":23,"correct":24},"D","将其后续工作的开始时间推迟3天，并使总工期延长1天",true,"Δ＞TF对后续工作和总工期均有影响。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]