[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931095":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931095,603,1,"单选题","通常将PDCA的质量管理过程方法用于设备制造的全过程。下列选项中，对C过程的正确描述是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","为提供结果建立必要的目标和过程",false,{"key":16,"text":17,"correct":18},"B","对过程和设备进行监视和测量，并报告结果",true,{"key":20,"text":21,"correct":14},"C","采取措施，以持续改进过程业绩",{"key":23,"text":24,"correct":14},"D","实施的过程","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]