[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931090":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931090,603,1,"单选题","在网络计划优化中，资源有限一工期最短的优化目的在于( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","通过压缩计算工期以达到要求工期目标",false,{"key":16,"text":17,"correct":14},"B","寻求工程总费用最低的工期安排",{"key":19,"text":20,"correct":21},"C","寻求满足资源限制条件的最短工期安排",true,{"key":23,"text":24,"correct":14},"D","寻求在计划工期不变的条件下使资源运用最均衡的计划安排","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]