[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931082":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931082,603,1,"单选题","在工程网络计划中，某工作的最迟完成时间与其最早完成时间的差值是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该工作的总时差",true,{"key":16,"text":17,"correct":18},"B","该工作的自由时差",false,{"key":20,"text":21,"correct":18},"C","该工作与其紧后工作之间的时间间隔",{"key":23,"text":24,"correct":18},"D","该工作的持续时间","工作总时差等于工作最迟开始时间减最早开始时间。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]