[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931081":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931081,603,1,"单选题","①确定对策；②确定每种对策的负责人与完成日期；③为工序编号；④确定存在问题。下列正确的对策表应用顺序为( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":14},"B","③①②④",{"key":19,"text":20,"correct":14},"C","①②④③",{"key":22,"text":23,"correct":24},"D","③④①②",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]