[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931080":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931080,603,1,"单选题","( )是指项目活动或工作分解结构组成部分已完成的价值，用分配给该工作的预算来表示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划价值",false,{"key":16,"text":17,"correct":18},"B","挣值",true,{"key":20,"text":21,"correct":14},"C","实际成本",{"key":23,"text":24,"correct":14},"D","机会成本","挣值(EV)也称赢得值或已完工作量的预算成本。是指项目活动或工作分解结构组成部分已完成的价值，用分配给该工作的预算来表示。挣值EV的计算公式为：挣值(EV)=已完工作量×预算单价挣值(EV)的实质内容是将已完成的工作量用预算费用来度量，主要反映该项目任务按合同计划实施的进展状况。这个参数具有反映费用和进度执行效果的双重特性，回答了这样的问题：到底完成了多少工作。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]