[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931068":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":9},931068,603,2,"多选题","",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","该工作提前1周完成",true,{"key":16,"text":17,"correct":14},"B","在第7周内实际完成的任务量超过计划任务量",{"key":19,"text":20,"correct":14},"C","第四周停工1周",{"key":22,"text":23,"correct":24},"D","在第3周内实际完成的任务量比计划任务量少6%",false,{"key":26,"text":27,"correct":24},"E","在第5周内实际进度与计划进度一致","ABC",{"id":6,"name":30,"category":31,"favorite":32},"质量、投资、进度控制","建筑工程",0]