[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931063,603,1,"单选题","在项目财务分析中，可判定项目可行的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","静态投资回收期小于行业标准投资回收期",true,{"key":16,"text":17,"correct":18},"B","财务内部收益率小于基准收益率",false,{"key":20,"text":21,"correct":18},"C","总投资收益率低于同行业收益率参考值",{"key":23,"text":24,"correct":18},"D","财务净现值率小于零","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]