[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931059,603,1,"单选题","建设工程组织流水施工时，相邻专业工作队之间的流水步距不尽相等，但专业工作队数等于施工过程数的流水施工方式是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","固定节拍流水施工和加快的成倍节拍流水施工",false,{"key":16,"text":17,"correct":14},"B","加快的成倍节拍流水施工和非节奏流水施工",{"key":19,"text":20,"correct":14},"C","固定节拍流水施工和一般的成倍节拍流水施工",{"key":22,"text":23,"correct":24},"D","一般的成倍节拍流水施工和非节奏流水施工",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]