[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931058":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931058,603,2,"多选题","与工程网络计划方法相比，横道图进度计划方法的优点是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","适用于手工编制计划",false,{"key":16,"text":17,"correct":14},"B","适应大的进度计划系统",{"key":19,"text":20,"correct":21},"C","便于项目进展状况的检查",true,{"key":23,"text":24,"correct":21},"D","便于统计完成计划所需资源的时间分布",{"key":26,"text":27,"correct":14},"E","清楚地显示各工作之间相互联系和制约的关系","CD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]