[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931056,603,1,"单选题","下列关于净现值的说法，正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","若项目的净现值小于零，则项目生产期利润肯定小于零",false,{"key":16,"text":17,"correct":14},"B","若项目的净现值大于零，则投资回收期肯定大于基准投资回收期",{"key":19,"text":20,"correct":21},"C","若项目的净现值大于零，则净年值也肯定大于零",true,{"key":23,"text":24,"correct":14},"D","若项目的净现值等于零，则项目生产期利润肯定等于零","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]