[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931055":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":9},931055,603,2,"多选题","",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","关键线路有2条",true,{"key":16,"text":17,"correct":14},"B","工作1～3与工作3～6的总时差相等",{"key":19,"text":20,"correct":21},"C","工作4～7与工作5～7的自由时差相等",false,{"key":23,"text":24,"correct":14},"D","工作2～6的总时差与自由时差相等",{"key":26,"text":27,"correct":21},"E","工作3～6的总时差与自由时差不等","ABD",{"id":6,"name":30,"category":31,"favorite":32},"质量、投资、进度控制","建筑工程",0]