[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},931054,603,1,"单选题","在工程网络计划执行中，如果某项工作进度拖延的时间超过了该项工作的总时差，在确定进度计划的调整方法时，则需要考虑( )的限制条件。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","后续工作最早开始时间",false,{"key":16,"text":17,"correct":14},"B","关键节点的最早时间",{"key":19,"text":20,"correct":14},"C","紧后工作最早开始时间",{"key":22,"text":23,"correct":24},"D","后续工作和总工期",true,"",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]