[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931042":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931042,603,1,"单选题","财务净现值为零，表明项目盈利能力水平( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","大于基准收益率",false,{"key":16,"text":17,"correct":14},"B","小于基准收益率",{"key":19,"text":20,"correct":21},"C","等于基准收益率",true,{"key":23,"text":24,"correct":14},"D","等于零","根据定义，显然NPV(ic)=O表示项目刚好达到所预定的收益率水平；NPV(ic)＞O意味着除保证项目可实现预定的收益外，尚可获得更高的收益；NPV(ic)＜O仅表示项目未能达到所预定的收益率水平，但不能确定项目已亏损。因此净现值法的评价标准为：NPV(ic)≥O，考虑接受该项目；NPV(ic)＜O，考虑拒绝该项目。",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]