[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931037":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931037,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","在第5周末工作C进度尚有总时差1周",false,{"key":16,"text":17,"correct":18},"B","在第5周末工作E进度拖后且影响工期1周",true,{"key":20,"text":21,"correct":14},"C","在第9周末整体工程进度拖后1周",{"key":23,"text":24,"correct":14},"D","在第9周末工作F尚有时差2周",{"key":26,"text":27,"correct":18},"E","在第9周末工作H进度拖后，影响工作1周","BE","工作C原有总时差1周，第5周末工作C进度拖后2周，尚有总时差-1周；工作E为关键工作，第5周末工作E进度拖后1周，预计影响工期1周；工作F原有总时差2周，第9周末工作F拖后1周，尚有时差1周；工作H原有总时差1周，第9周末工作F拖后2周，尚有时差-1周，预计影响工期1周。",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]