[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931035":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931035,603,2,"多选题","建设工程静态投资包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建筑安装工程费",true,{"key":16,"text":17,"correct":14},"B","设备工器具购置费",{"key":19,"text":20,"correct":14},"C","工程建设其他费",{"key":22,"text":23,"correct":14},"D","基本预备费",{"key":25,"text":26,"correct":27},"E","土地使用税",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]