[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931028":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},931028,603,1,"单选题","当采用匀速进展横道图比较法时，如果表示实际进度的横道线右端点位于检查日期的右侧，则该端点与检查日期的距离表示工作( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实际少消耗的时间",false,{"key":16,"text":17,"correct":14},"B","实际多消耗的时间",{"key":19,"text":20,"correct":21},"C","进度超前的时间",true,{"key":23,"text":24,"correct":14},"D","进度拖后的时间","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]