[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931023":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931023,603,2,"多选题","在工程建设施工阶段，当通过压缩网络计划中关键工作的持续时间来缩短工期时，通常采取的技术措施有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用更先进的施工方法",true,{"key":16,"text":17,"correct":18},"B","增加劳动力和施工机械的数量",false,{"key":20,"text":21,"correct":14},"C","改进施工工艺和施工技术",{"key":23,"text":24,"correct":18},"D","改善劳动条件",{"key":26,"text":27,"correct":14},"E","采用更先进的施工机械","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"质量、投资、进度控制","建筑工程",0]