[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931022":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},931022,603,1,"单选题","某工程网络计划中，工作A的最早开始时间为第20天，持续时间为7天，该工作有三项紧后工作，它们的最迟开始时间分别为第43天、第30天和第33天，则工作A的总时差为( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","6",false,{"key":20,"text":21,"correct":18},"C","10",{"key":23,"text":24,"correct":18},"D","16","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]