[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931021":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":9},931021,603,2,"多选题","",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","第2周期间实际完成任务量超过计划2%",true,{"key":16,"text":17,"correct":18},"B","该设备焊接过程未按原计划开始",false,{"key":20,"text":21,"correct":14},"C","到第3周末该过程实际累计完成任务量与计划进度一致",{"key":23,"text":24,"correct":14},"D","第4周该设备焊接过程出现停工",{"key":26,"text":27,"correct":18},"E","该设备焊接过程按计划完成","ACD",{"id":6,"name":30,"category":31,"favorite":32},"质量、投资、进度控制","建筑工程",0]