[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},931020,603,1,"单选题","某双代号网络计划，已知工作K的持续时间为7天，最迟完成时间为第30天。工作K有三项紧前工作，它们的最早完成时间分别是第13天、第15天和第17天，则工作K的总时差为( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":18},"B","6",true,{"key":20,"text":21,"correct":14},"C","8",{"key":23,"text":24,"correct":14},"D","10","",{"id":6,"name":27,"category":28,"favorite":29},"质量、投资、进度控制","建筑工程",0]