[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931017":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931017,602,2,"多选题","工程师可以指示承包商提交一份更新的进度计划的情形有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","承包商的实际进度过慢可能导致无法在竣工时间内完成全部设备工程",true,{"key":16,"text":17,"correct":18},"B","承包商的实际进度过快可能导致在竣工时间届满前完成全部设备工程",false,{"key":20,"text":21,"correct":14},"C","异常不利的气候条件致使实际进度落后于承包商的现行进度计划",{"key":23,"text":24,"correct":14},"D","业主人员造成的延误致使实际进度落后于承包商的现行进度计划",{"key":26,"text":27,"correct":18},"E","业主雇用在现场的其他承包商提前完工致使实际进度提前于承包商的现行进度计划","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]