[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931015":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931015,602,2,"多选题","在设备工程合同履行过程中，也会发生业主索赔。下列关于业主索赔权利的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","业主应在发生索赔事件后的28天内，提交索赔报告",false,{"key":16,"text":17,"correct":18},"B","业主索赔的内容包括有权得到的付款、缺陷通知期延长",true,{"key":20,"text":21,"correct":14},"C","业主索赔的内容包括费用、利润和竣工时间",{"key":23,"text":24,"correct":18},"D","业主要求延长缺陷通知期的，应在缺陷通知期期满前发出通知",{"key":26,"text":27,"correct":18},"E","业主的索赔额确定后，可从合同价格和支付证书中扣除","BDE","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]