[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931012":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931012,602,2,"多选题","对于分段移交的设备工程，保留金的退还程序有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","单位工程移交时，退还与该单位工程价值相当的保留金的40%",true,{"key":16,"text":17,"correct":18},"B","单位工程移交时，退还与该单位工程价值相当的保留金的50%",false,{"key":20,"text":21,"correct":14},"C","单位工程缺陷通知期期满时，再退还40%",{"key":23,"text":24,"correct":18},"D","单位工程缺陷通知期期满时，再退还50%",{"key":26,"text":27,"correct":14},"E","在最后一个单位工程的缺陷通知期期满时，退还剩余的保留金","ACE","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]