[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931010":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931010,602,2,"多选题","设备工程的竣工试验程序通常包括的阶段有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","审核承包商文件",false,{"key":16,"text":17,"correct":18},"B","启动前试验",true,{"key":20,"text":21,"correct":18},"C","启动试验",{"key":23,"text":24,"correct":18},"D","试运行",{"key":26,"text":27,"correct":14},"E","签署试验报告","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]