[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-931005":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},931005,602,2,"多选题","如果工程师发出了暂停指示，承包商在遵守该指示或在复工时招致了费用损失和工期延误，承包商无权获得补偿的情形有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","由于承包商提供的设计存在缺陷造成的暂停",true,{"key":16,"text":17,"correct":14},"B","由于承包商提供的材料存在缺陷造成的暂停",{"key":19,"text":20,"correct":14},"C","由于承包商提供的设备存在缺陷造成的暂停",{"key":22,"text":23,"correct":14},"D","承包商未能在工程暂停时，按合同规定提供相应的安全保护措施",{"key":25,"text":26,"correct":27},"E","承包商已经遵守了地方政府部门制定的程序",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]