[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930991":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930991,602,2,"多选题","设备工程合同有很强的不可预见性，导致合同价格变化的原因有( )",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","市场因素",true,{"key":16,"text":17,"correct":14},"B","工程所在地法律、法规、条例、细则等发生变化",{"key":19,"text":20,"correct":14},"C","工程变更",{"key":22,"text":23,"correct":14},"D","误期损害赔偿费和提前竣工奖金",{"key":25,"text":26,"correct":27},"E","不可抗力",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]