[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930990":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930990,602,2,"多选题","设备工程合同中，对设备工程接收条件的约定通常有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程已按合同约定基本完成并通过了竣工试验",true,{"key":16,"text":17,"correct":18},"B","工程已按合同约定全部完成并通过了竣工试验",false,{"key":20,"text":21,"correct":14},"C","工程师已签发了工程接收证书",{"key":23,"text":24,"correct":18},"D","承包商已经完成了全部扫尾工作",{"key":26,"text":27,"correct":18},"E","业主组织了联合检查，并形成书面文件","AC","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]