[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930985":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930985,602,2,"多选题","评标过程中，初步评审的主要内容包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","投标人的合格性",true,{"key":16,"text":17,"correct":14},"B","投标担保",{"key":19,"text":20,"correct":14},"C","资格证明文件",{"key":22,"text":23,"correct":14},"D","业绩",{"key":25,"text":26,"correct":27},"E","报价的合理性",false,"ABCD","报价的合理性应当在详评中进行评审。",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]