[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930983":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930983,602,2,"多选题","设备工程合同履行过程中，合同控制主要有( )阶段控制。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设计",true,{"key":16,"text":17,"correct":14},"B","采购",{"key":19,"text":20,"correct":14},"C","制造",{"key":22,"text":23,"correct":24},"D","生产运营",false,{"key":26,"text":27,"correct":14},"E","安装","ABCE","设备工程合同履行过程中，合同控制主要有设计、采购、制造、安装阶段控制，生产运营阶段已经不属于设备合同履行阶段。",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]