[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930976":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930976,602,2,"多选题","在设备工程合同中，完成工程的含义有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","通过了竣工试验",true,{"key":16,"text":17,"correct":18},"B","完成了合同规定的工程或单位工程的全部工作",false,{"key":20,"text":21,"correct":14},"C","完成了合同规定的工程或单位工程接收所要求完成的全部工作",{"key":23,"text":24,"correct":18},"D","修补了无论在工程实施过程，还是在缺陷通知期内发现的质量缺陷",{"key":26,"text":27,"correct":18},"E","完成了履约证书所证明的全部工作","AC","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]