[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930975":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930975,602,2,"多选题","采用FIDIC合同条件的设备工程合同，承包商根据工程师指示提交的变更建议书，应当包括的内容有( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","变更工作说明",true,{"key":16,"text":17,"correct":14},"B","变更工作进度计划",{"key":19,"text":20,"correct":14},"C","对整个设备工程计划进行调整的建议",{"key":22,"text":23,"correct":14},"D","变更工作的价格",{"key":25,"text":26,"correct":27},"E","变更导致的索赔金额",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]