[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930950":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930950,602,2,"多选题","根据FIDIC《生产设备和设计一施工合同条件》的规定，雇主应承担由于战争而导致的( )损失或损坏的风险。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程",true,{"key":16,"text":17,"correct":14},"B","货物",{"key":19,"text":20,"correct":14},"C","承包商文件",{"key":22,"text":23,"correct":24},"D","工程师文件",false,{"key":26,"text":27,"correct":24},"E","承包商设备","ABC","战争属于业主风险，如果此类业主风险达到对工程、货物、或承包商文件造成损失或损害的程度，承包商应立即通知雇主，并应按雇主要求，修整此类损失或损害。如果因此招致增加费用，承包商应进一步向雇主索赔。",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]