[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930946":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930946,602,2,"多选题","相对其他合同计价方式而言，固定单价合同的优点有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制工程量清单不需要花费一定的物质成本和时间成本",false,{"key":16,"text":17,"correct":18},"B","承包商所做的每项工作都能在合同价格中得到体现，承包商能够根据工程量估算自己的工作范围并据此制订适当的实施计划",true,{"key":20,"text":21,"correct":18},"C","如果工作范围不发生变化，业主的财务支出将是固定的",{"key":23,"text":24,"correct":18},"D","填入单价的工程量清单有利于业主通过汇总价评判投标人的报价优劣情况",{"key":26,"text":27,"correct":14},"E","在一定程度上可激励承包商降低成本，以提高单位直接成本的效益","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]