[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930942":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930942,602,2,"多选题","根据FIDIC《生产设备和设计一施工合同条件》，承包商实施工程期间，遭遇不可预见的物质条件时，有权索赔工期和费用。该物质条件包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","现场地质条件",true,{"key":16,"text":17,"correct":14},"B","现场人为的物质障碍",{"key":19,"text":20,"correct":14},"C","现场污染物",{"key":22,"text":23,"correct":14},"D","现场水文条件",{"key":25,"text":26,"correct":27},"E","现场气候条件",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]