[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930941":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930941,602,2,"多选题","根据FIDIC《生产设备和设计一施工合同条件》，下列关于索赔事件处置的说法，正确的有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","索赔通知应在索赔事件发生后合同规定的时间内发出",true,{"key":16,"text":17,"correct":14},"B","如果承包商未发出索赔通知，则视为承包商放弃索赔权利",{"key":19,"text":20,"correct":21},"C","索赔款额应列入最终付款证书中，并支付给承包商",false,{"key":23,"text":24,"correct":14},"D","工程师应对承包商的索赔报告作出回应",{"key":26,"text":27,"correct":21},"E","工程师收到承包商的索赔通知后，应做好索赔事件的同期记录","ABD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]