[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930938":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930938,602,2,"多选题","设备工程合同履行中发生的下列情况中，按照《合同法》对不可抗力免责的规定，承包人不承担责任的有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","洪水灾害导致工程受损",true,{"key":16,"text":17,"correct":14},"B","地震灾害导致工程受损",{"key":19,"text":20,"correct":14},"C","社会动乱导致停工损失",{"key":22,"text":23,"correct":24},"D","承包人安全管理制度不落实导致火灾损失",false,{"key":26,"text":27,"correct":24},"E","承包人拖欠工人工资导致罢工的停工损失","ABC","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]