[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930932":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930932,602,2,"多选题","在设备工程合同中，特殊事件的处理机制主要有( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","暂停施工的处理机制",false,{"key":16,"text":17,"correct":14},"B","法律变动处理机制",{"key":19,"text":20,"correct":14},"C","市场价格波动处理机制",{"key":22,"text":23,"correct":24},"D","索赔和争端的解决机制",true,{"key":26,"text":27,"correct":24},"E","不可抗力的处理机制","DE","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]