[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930929":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930929,602,2,"多选题","属于设备工程合同变更的情况有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","业主的变更要求",true,{"key":16,"text":17,"correct":14},"B","承包商提出的变更建议，并经业主批准",{"key":19,"text":20,"correct":21},"C","业主提出的变更建议，并经承包商批准",false,{"key":23,"text":24,"correct":21},"D","承包商管理制度调整",{"key":26,"text":27,"correct":21},"E","政府领导的决定","AB","在签发接收证书之前，工程师可以通过两种方式提出变更：直接发出变更指示，或请求承包商提交变更建议书。工程师属于业主人员，工程师的行为应当认为是代表业主作出的。",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]