[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930920":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930920,602,2,"多选题","在设备采购合同中，买受人的验收依据包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","双方签订的设备采购合同",true,{"key":16,"text":17,"correct":18},"B","运输方提供的发货单、计量单、装箱单及其他有关凭证",false,{"key":20,"text":21,"correct":18},"C","设备运输合同",{"key":23,"text":24,"correct":14},"D","产品合格证、检验单",{"key":26,"text":27,"correct":14},"E","图纸、样品或其他技术证明文件","ADE","验收的依据包括：双方签订的采购合同；供货方提供的发货单、计量单、装箱单及其它有关凭证；合同内约定的质量标准。应写明执行的标准代号、标准名称；产品合格证、检验单；图纸、样品或其他技术证明文件。",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]