[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930903":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930903,602,2,"多选题","为进行除竣工后试验(如果有)以外的合同规定的所有试验，承包商应提供试验所需的( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","试验场地",false,{"key":16,"text":17,"correct":18},"B","合格的人员，包括职员和劳务",true,{"key":20,"text":21,"correct":14},"C","任何的试验费用",{"key":23,"text":24,"correct":18},"D","设施和仪器",{"key":26,"text":27,"correct":18},"E","消耗品，包括电、燃料、材料等","BDE","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]