[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930898":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930898,602,2,"多选题","设备工程合同履行期间，承包人具有( )情形的，发包人有权请求解除该设备工程合同。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","明确表示不履行合同主要义务的",true,{"key":16,"text":17,"correct":18},"B","采用不合格的材料进行施工的",false,{"key":20,"text":21,"correct":14},"C","将承包的设备工程非法转包、违法分包的",{"key":23,"text":24,"correct":14},"D","已经完成的建设工程质量不合格，并拒绝修复的",{"key":26,"text":27,"correct":18},"E","不能在合同约定的期限内完工的","ACD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]