[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930883":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930883,602,2,"多选题","采用FIDIC合同条件的设备工程合同，工程师提出变更的方式有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","由业主向承包商提出建议书",false,{"key":16,"text":17,"correct":18},"B","工程师请求承包商提交变更建议书",true,{"key":20,"text":21,"correct":14},"C","工程师向承包商发出变更建议书",{"key":23,"text":24,"correct":18},"D","工程师直接发出变更指示",{"key":26,"text":27,"correct":14},"E","由业主直接发出变更指示","BD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]