[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930881":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930881,602,2,"多选题","设备工程合同正式签字前，当事人双方应进行的工作包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","审查合同文件是否符合法律、行政法规、相关标准规范的规定",true,{"key":16,"text":17,"correct":14},"B","审查合同的完备性",{"key":19,"text":20,"correct":14},"C","审查合同双方的责、权、义的对等性",{"key":22,"text":23,"correct":14},"D","审查合同语言文字的准确性",{"key":25,"text":26,"correct":27},"E","审查进度报告的合理性",false,"ABCD","设备工程合同正式签字前，当事人双方的代表或其助手要对准备签字的正式文本与草签的文本再重新复核。双方应进行下列工作：(1)审查合同文件是否符合法律、行政法规、相关标准规范的规定。(2)审查合同的完备性。(3)审查合同双方的责、权、义的对等性。(4)审查合同语言文字的准确性。",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]