[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930871":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930871,602,2,"多选题","设备工程合同履行中，承包商提交工程师审核的承包商文件包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","操作和维修手册",true,{"key":16,"text":17,"correct":14},"B","合同规定的竣工文件",{"key":19,"text":20,"correct":21},"C","质量管理内审文件",false,{"key":23,"text":24,"correct":21},"D","指定分包商的资质文件",{"key":26,"text":27,"correct":14},"E","业主要求中规定的技术文件","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]