[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930868":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930868,602,2,"多选题","导致承包商无法在合同规定的竣工时间内完成整个设备工程或单位工程，承包商有权要求延长竣工时间的情形有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","雨雪天气不利于现场施工",false,{"key":16,"text":17,"correct":18},"B","合同变更或某些工作量有大量变化",true,{"key":20,"text":21,"correct":18},"C","流行病导致的无法预见的人员短缺",{"key":23,"text":24,"correct":18},"D","当地政府原因导致的无法预见的物品短缺",{"key":26,"text":27,"correct":14},"E","在现场的指定分包商造成的延误","BCD","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]