[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930867":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930867,602,2,"多选题","因不可抗力终止合同后，工程师开出的付款证书中通常包括的内容有( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","合同中标明的已完成的任何工作价值",true,{"key":16,"text":17,"correct":14},"B","合同终止时承包商人员和设备遣返回公司注册地的费用",{"key":19,"text":20,"correct":21},"C","承包商将施工设备运至公司其他工地的费用",false,{"key":23,"text":24,"correct":21},"D","因不可抗力招致的承包商利润损失",{"key":26,"text":27,"correct":14},"E","承包商在不可抗力情况下为完成工程而招致的合理开支","ABE","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]