[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-930864":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},930864,602,2,"多选题","下列关于FIDIC新黄皮书对预付款扣减方式规定的说法，正确的有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","当已确认的期中付款的累计金额超过中标合同金额减去暂定金额后余额的10%时开始扣还预付款",true,{"key":16,"text":17,"correct":18},"B","当已确认的期中付款的累计金额超过中标合同金额减去暂定金额后余额的20%时开始扣还预付款",false,{"key":20,"text":21,"correct":18},"C","每次扣还预付款的金额为当期付款证书金额的10%",{"key":23,"text":24,"correct":14},"D","每次扣还预付款的金额为当期付款证书金额的25%",{"key":26,"text":27,"correct":14},"E","按照预付款的货币和比例计算","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"设备监理合同管理","建筑工程",0]